Tweed Shire Council Flood Recovery Works

LOCATION
Tweed Shire, Northern NSW

PROJECT VALUE
$3.4 million

PROJECT DURATION
3 years

Introduction

RCC Civil was engaged by Tweed Shire Council to deliver a large-scale, multi-site flood recovery program following severe storm and rainfall events across the region.

Spanning more than 400 individual repair sites, the works focused on restoring access, stabilising damaged assets, and strengthening infrastructure resilience under challenging weather and access conditions.

Client / Partner

Tweed Shire Council

A long-term council partner, RCC Civil was selected for our proven track record in flood recovery, drainage delivery, and safe, coordinated project management across the Northern Rivers.

Scope OF Works:

The scope of works included flood recovery and reinstatement across more than 400 sites, including:

Slope and batter repairs following landslips

Culvert replacements and drainage reinstatement

Pavement, subgrade, and seal repairs

Unsealed road regrading and reconstruction

Bridge approach and abutment repairs

Debris removal and environmental protection measures

Works were delivered across urban and regional locations, requiring careful sequencing and coordination to minimise disruption and manage safety risks.

Challenges

The program involved working across hundreds of geographically dispersed sites, many with restricted access and ongoing weather exposure.

Maintaining safety, environmental compliance, and community access while meeting emergency works funding requirements required a highly structured and adaptable delivery approach.

Solutions Delivered

RCC Civil provided rapid mobilisation and a coordinated delivery model supported by in-house crews, plant, and digital project management systems.

Using structured scheduling, real-time reporting, and close collaboration with council stakeholders, the team prioritised high-risk sites and managed efficient sequencing across the program.

Early identification of access constraints and environmental sensitivities allowed works to proceed safely and compliantly, even under changing site conditions.

Outcome / Impact

All sites were completed safely and in accordance with emergency works requirements, restoring access for local communities and strengthening critical infrastructure across the Tweed Shire.

RCC Civil’s coordinated approach enabled the council to meet funding timelines, reduce ongoing risk, and prioritise locations with the greatest impact on public safety and connectivity.